|
|
|
Construction Work - April 2018
|
Construction Work - April 2018
|
Construction Work - April 2018
|
|
|
|
Construction Work - April 2018
|
Construction Work - April 2018
|
Construction Work - April 2018
|
|
|
|
Views-Columns works for 3rd to 4th floor in progress
|
Views-Columns works for 3rd to 4th floor in progress
|
Views-Columns works for 3rd to 4th floor in progress
|
|
|
|
Side View-Columns From 3rd to 4th in progress
|
Front View-Columns From 3rd to 4th in progress
|
Top View- Shuttering & Reinforcement-1st Floor, Pour 2
|
|
|
|
Side View- Casted Columns- Ground Floor, Pour 2
|
Casted Slab-Ground Floor
|
Ground Floor Slab
|
|
|
|
Casted Slab-3rd Floor, Pour 1
|
Column Reinforcement 3rd to 4th Floor, Pour 1
|
Upper Basement Slab Concreting |
|
|
|
Column Casting Second to Third Floor |
Casting of STP Walls |
Curing of Upper Basement Roof Slab |
|
|
|
De-Shuttering of Columns |
Shuttering at Third Floor Level |
Shuttering of Lift Wall |
|
Curing at Upper Basement Roof Level |